Analysis
Nexans wins over 50 million Euro contract to supply high-voltage power cable for Northwind offshore wind farm
Nexans has won a contract worth more than 50 million Euro to supply a total of 57 km of high-voltage subsea power export cables to Northwind NV in the North Sea. The project comprises 14 km of cable to connect Belwind Phase 2 to the Northwind wind farm (formerly known as Eldepasco), together with a further 43 km of cable that will transfer a total of 381 MW produced by both wind farms to the onshore grid connection at Zeebrugge.
In aThe Northwind wind farm will comprise 72 wind turbines, summing up to a total of 216 MW installed capacity. The power will be delivered to the Belgian electricity network at the ELIA HV connection station in Zeebrugge. The 14 km section of 245 kV cable connecting Belwind Phase 2 to Northwind will consist of three copper cores, each with a cross-section of 400 mm2.
The majority of the 43 km, 245 kV connection from Northwind to Zeebrugge will comprise of three 1000 mm2 copper cores. However, there is a length of the route where the cable has to traverse a sea channel subjected to regular dredging, requiring it to be buried down to 9 metres in the seabed for protection. In order to maintain the electrical performance of the cable along this channel, the copper cross-section will be increased to 1200 mm2 on a 4 km section. This section of cable will have an outer diameter of 265 mm and will weigh 130 kg per meter.
The subsea cables will be manufactured at Nexans’ specialized facility in Halden, Norway. They will also include two FO48 fiber optic elements, manufactured in the Nexans Rognan plant, to enable data communications, control and monitoring for the power transmission system.