Freescale updates plans for Sendai fabrication facility
After completing the assessment of its Sendai, Japan wafer fabrication facility following the recent earthquake, Freescale Semiconductor today announced that it will not reopen the seriously damaged facility.
The When the earthquake struck off the coast of Sendai, the factory immediately ceased operations and all employees were safely evacuated. Freescale subsequently confirmed that all of its employees and contractors had survived the earthquake and resulting tsunami. The company immediately commenced humanitarian efforts to assist its employees and their families. Freescale also began a preliminary assessment of the Sendai facility to determine the extent of the damage and how it might return to full or partial production in a safe and timely manner.
“In this time of devastating loss for many of our Sendai employees, we want to do what we can to help and to return some sense of stability to their lives,” said Rich Beyer, Freescale’s Chairman and CEO. “To that end, Freescale will compensate them through a salary continuation for an extended period of time, coupled with a comprehensive severance package.”
In April 2009, Freescale announced plans to close its Sendai operations in 2011. Prior to the earthquake and tsunami, the company planned to complete the closure of the facility in December 2011.
The Sendai facility produces microcontrollers, analog ICs and sensors products. In anticipation of the previously announced closure, Freescale has been building buffer inventory to support end-of-life products and the transfer of production from Sendai to Freescale’s other fabs and outside foundry partners. This buffer inventory has been stored in other Freescale facilities and was not affected by the events in Japan. In addition, some products produced in the Sendai facility have been qualified in other Freescale locations, while other products are in the process of being transferred.
Freescale is continuing to assess the impact of this natural disaster on its entire supply chain in an effort to minimize the effect on its customers’ operations and has initiated a number of actions to address supply gaps, including:
Use of buffer inventories already built in anticipation of the previously announced Sendai factory closure;
Partnering with customers to substitute compatible, alternate devices where viable;
Production ramp of products already qualified in Freescale’s semiconductor fabrication facilities in Oak Hill, Texas and Chandler, Arizona, or foundry partners;
Working with customers to accelerate the ongoing transition of products to Freescale’s other facilities or foundry partners; and
Adding capacity earlier than planned for select technologies that are being transferred to Freescale’s alternate fabrication facilities.